9.4. Action to be taken.- If the results of the
preliminary inspection, taken in the light of the
discussion which follows, indicate that a sacrificial
anode protection system consisting of less than
six anodes will afford the necessary protection,
O&M personnel may wish to proceed with the
installation. If, on the other hand, it appears that a
larger sacrificial anode system, an impressed
current system, or other measures may be
required, the problem should be presented to the
Operation and Maintenance Engineering Branch,
Denver Office, Attention D-5850, for coordination
with the Division of Design. In so doing, it is
important to supply the information listed in the
appropriate questionnaire (appendix) so that the
initial letter will furnish the data required for
analysis of the problem.
(FIST 4-5) 18